The project is behind schedule. David Irwin, president of the developer, Irwin Development Group, said Monday the project was originally scheduled to start construction in May but is now on hold until at least September.
With the COVID-19 economic crisis further complicating the project, Irwin Development Group and the city agency are now seeking to rewrite some of the terms of a development agreement, he said.
Both sides point fingers at the other, claiming they missed deadlines and set excessive demands, according to communications provided to the Anchorage Daily News by Matt Singer with Holland & Knight law firm, representing Irwin Development.
Andrew Halcro, executive director of the Anchorage Community Development Authority, said on Monday he could not discuss details of the dispute.
The authority has worked with the developer on the project for almost three years, he said in a text.
“We continue to try and find a path forward,” he said.
Part of the dispute involves a $350,000 security deposit that the development authority wants from Irwin Development, according to Irwin. If the city backs out of the project, $175,000 of that deposit would not be refunded, he said.
The authority threatened to terminate the deal on Thursday if the demands were not met, he said. As of Monday, Irwin Development had not accepted the terms but had received no response from the authority, he said.
“They seem dead-set on ending this project and I don’t know why,” Irwin said.
The 12-story Hotel Indigo, at Sixth Avenue between G and H streets, would be anchored against and supported by the eight-story EasyPark parking garage that’s run by the authority.
It would be the first major hotel construction in the area since the Anchorage Marriott Downtown was built about 20 years ago. To speed up construction, rooms would be pre-built in China and shipped to Anchorage by barge.
Irwin said the planned work in China, where the virus that causes COVID-19 was first identified last year, did not contribute to a delay in the project.
Instead, the development authority was required to temporarily relocate the city’s transit center and buses, located at the site, before construction could begin in May, he said.
But in January, Chris Schutte, director of the city’s Office of Economic and Community Development, said the move could not take place by May, Irwin said. Schutte did not return requests for comment for this article.
The confusion created uncertainty for project investors, challenging efforts to finalize fundraising, Irwin said.
On May 1, the authority confirmed the bus-center relocation would happen by late August, four months later than originally planned, Irwin said.
Also, the global economic collapse caused by COVID-19 began in March, creating an extraordinary unplanned event that added to investor anxiety, he said.
The authority says Irwin Development should have completed raising finances for the project by April 1, according to a 15-page letter from Holland & Knight and addressed to Diana Parks with Dorsey & Whitney, the law firm representing the authority.
But the attorneys for Irwin Development dispute that, in part because of the delayed bus-center move, according to the letter, dated Thursday.
Also, the pandemic is considered a “force majeure" under the development agreement and ground lease between the parties.
Such an event — often called an act of God — allows an extension of all the contractual deadlines, an attorney for Irwin Development says in the letter.
“ACDA is attempting to use this supposed ‘failure’ as a cudgel to extort an additional $350,000 security deposit from Irwin Development Group, of which $175,000 can be lost by Irwin Development Group through no fault of its own,” the letter says.
Irwin Development has provided the additional financial paperwork for the rent relief, Irwin said.
If things can’t be resolved to move the project ahead, he’ll consider bringing a lawsuit against the development authority.
“We want to build a hotel,” Irwin said. “I’m not in this business to bring a lawsuit. I’m in this business to build buildings.”
[Because of a high volume of comments requiring moderation, we are temporarily disabling comments on many of our articles so editors can focus on the coronavirus crisis and other coverage. We invite you to write a letter to the editor or reach out directly if you’d like to communicate with us about a particular article. Thanks.]
"hotel" - Google News
June 09, 2020 at 10:11AM
https://ift.tt/2MJ5Epc
$60 million Anchorage hotel project delayed amid disagreement between developer and city agency - Anchorage Daily News
"hotel" - Google News
https://ift.tt/3aTFdGH
https://ift.tt/2xwvOre
Bagikan Berita Ini
0 Response to "$60 million Anchorage hotel project delayed amid disagreement between developer and city agency - Anchorage Daily News"
Post a Comment